To service growth and traffic demands, and provide new travel options, Halton Region is extending William Halton Parkway (Regional Road 40) to create a new east-west corridor from Bronte Road (Regional Road 25) to Ninth Line (Regional Road 13) in Oakville.

About this project

Construction of the new corridor is happening in two phases and Phase 1 started in 2018. Residents and motorists can expect to see a new, complete corridor with the following improvements between Third Line and Ninth Line:

  • New roadway
  • Roundabouts
  • Traffic signals
  • Bridges
  • Sewer back up prevention
  • Maintaining clean drinking water
  • Multi-use pathways
  • Bike lanes
  • Sidewalks

Project updates

To service growth and increasing traffic demands, Halton Region is pleased to announce that the new William Halton Parkway West (Reg. Rd. 40), from Sixth Line to Neyagawa Boulevard (Reg. Rd. 4) on November 3, 2023, Ward 7, in the Town of Oakville, is now open.

This road extension provides safe travel options to motorists, pedestrians, cyclists and first responders. William Halton Parkway West now has:

  • a new 4-lane roadway between Sixth Line and Neyagawa Blvd (Reg. Rd. 4);
  • new on-road bike lanes, multi-use pathways and sidewalks;
  • new street lighting and landscaping; and
  • a new non-signalized intersection at William Halton Parkway West and Burnhamthorpe Road West

Please Note: Intermittent construction works may continue to take place within the project limits following the road opening. Please exercise caution when driving through any construction in the area.

Read the Notice of Road Opening (external link)

Project renderings and photographs

Explore the images below for what you can expect to see once improvements are complete.

Map

Map of William Halton Parkway construction phases

Renderings

View of William Halton Parkway at Sixth Line.
View of William Halton Parkway at Sixth Line.

Improvements include:

  • new two-lane road
  • new two-lane roundabout
  • new street lighting
  • new multi-use pathway
  • new landscaping
View of William Halton Parkway
View of William Halton Parkway.

Improvements include:

  • new two-lane road
  • new two-lane roundabout
  • new street lighting
  • new multi-use pathway
  • new landscaping
View of William Halton Parkway.
View of William Halton Parkway.

Improvements include:

  • new two-lane road
  • new two-lane roundabout
  • new street lighting
  • new multi-use pathway
  • new landscaping

Photographs

View of William Halton Parkway at Sixth Line.
Photograph of William Halton Parkway – Phase 2, Stage 1.
View of William Halton Parkway
Photograph of William Halton Parkway – Phase 2, Stage 1.

Project map

Project Timeline

Phase 1 Timeline

Phase 1

  • Environmental assessment completed.

  • Detailed design completed and construction contract awarded for Phase 1

  • Construction start for Phase 1.

  • Phase 1 complete.

Phase 2 Timeline

Phase 2

  • Environmental assessment completed.

  • Construction start for Phase 2

  • Projected completion for Phase 2

What you can expect day-to-day

Halton Region is making every effort to minimize the disruptions and help you plan ahead for construction activity the extension will create.

Learn more about what to expect day-to-day, our mitigation plans and how to stay connected on the project.

I’m a resident or business in the area

Advance notice of any service disruption or construction impacts will be provided to residents in-person, through letter, email and website updates.

Below are some impacts you may experience:

  • Traffic delays: The project may cause traffic delays, lane shifts or lane restrictions. We will make every effort to minimize any potential inconvenience and provide you with advance notice when disruptions must occur. Access for emergency vehicles (Fire, EMS and Police) will be maintained at all times.
  • Driveway access: During the project, direct access to your driveway may be restricted for short periods of time. You will be notified in advance of any planned restrictions.
  • Waste collection: Your garbage and recycling will continue to be picked up on the regular scheduled day. It is the contractor’s responsibility to move your garbage and recycling to a location where our collection vehicles can pick them up. Please mark your house number on your containers or bins to help with identification.
  • Mail delivery: We do not anticipate any changes or delays to mail delivery. In the event that there are any changes, you will be notified in advance.
  • Truck traffic: At times you will notice increased truck traffic in the construction area. Please be aware and use extra caution while driving, and while exiting your property.
  • Dust and mud: There may be increased levels of dust and mud near the work site. The contractor is required to manage these impacts.

I use the roads in this area

Advance notice of any closures or restrictions will be available through letter, email, social media, road signs and website updates.

The following mitigation strategies have been put in place to minimize the impact on traffic and travel:

  • Using electronic signs: Road signs will be on site to with up-to-date traffic impacts.

Latest traffic updates and notices

Traffic updates

Halton Region’s contractor will be using a section of Lions Valley Park and its parking lot as a construction staging area. Parking spots will be reduced and there may be delays in accessing the park using Lions Valley Park Road.

Sign up for email updates on Regional improvements

Stay up-to-date

Halton Region has a dedicated Construction Ambassador for this project who will be available to meet with residents and businesses to address any questions or concerns.

You can also stay connected by:

  • signing up to get the latest project and traffic updates by email;
  • following @RegionofHalton (external link) on Twitter for the latest updates;
  • emailing accesshalton@halton.ca or calling 311 with any questions; or
  • visiting this webpage for the latest information.